Construction Administration Costs and How to Reduce Them
Construction administration budgets often run over on repeat submittal reviews. See where CA costs come from and how engineering firms protect margins.

Reducing construction administration costs comes down to one variable most fee proposals don't price: how many times each submittal gets reviewed. Construction administration (CA) is the design team's work during construction, covering submittal and RFI review, site visits, payment applications, change orders, and closeout.
Most of those tasks follow the schedule. Resubmittals follow the quality of what the contractor sends, and every extra review cycle comes out of a fixed CA fee.
For engineering firm principals, this is often where a profitable job slides to break-even, and the slide rarely shows up in reports before closeout. The hours behind it are easy to count, though, and the five changes below bring them down.
What Do Construction Administration Costs Include?
Construction administration costs are the hours and expenses a design firm spends supporting construction after documents are issued. On most construction projects, they fall into six buckets.
CA cost bucket | What drives the hours | Fixed or variable? |
Site visits and OAC meetings | Contract frequency and project duration | Mostly fixed |
Payment applications and change orders | Billing cycle and change volume | Partly variable |
RFIs | Document clarity and project scope gaps | Variable |
Submittal review | Number of submittals times review cycles | Highly variable |
Substitution requests | Contractor-proposed alternates that need evaluation | Variable |
Closeout | Punch lists, O&M manuals, record documents | Mostly fixed |
How CA Costs Differ From Construction Cost
CA is part of professional fees, a small slice of total project cost next to hard costs like material costs, equipment, and labor. For the engineering firm, though, those professional services hours are direct costs against a fixed fee. The fixed buckets are easy to estimate from past projects. Submittal review is the outlier: the engineer prices one review per submittal, and the project often delivers two or three.
How Much Does Construction Administration Cost?
Construction administration typically gets about 20% of the design fee under the traditional rule of thumb. AIA guidance on budgeting the construction phase lays out the classic split:
Design phase | Share of fee |
Schematic design | 10% |
Design development | 25% |
Construction documents | 40% |
Bidding | 5% |
Construction contract administration | 20% |
The same AIA guidance shows why that percentage misleads. In its worked example, a 5,000-hour fee with a 24-month construction period leaves CA about 9.7 hours a week, roughly a quarter of a person. A two-year build needs far more CA time than a one-year build, and a flat percentage treats them the same.
Why Do Construction Administration Budgets Run Over?
Construction administration budgets run over because the budget is fixed when the owner agreement is signed, often a year or more before the first submittal arrives, while the workload is set later by duration, change volume, and review cycles. The AIA authors name the same causes:
An arbitrary percentage of the fee that ignores construction duration.
Fixed fees, so every added CA hour comes out of design and documentation hours.
Contractually required weekly site visits and meetings that leave little time for anything else.
Submittals, RFIs, pay requests, and change orders competing for the same thin hours.
As Tom Port, co-founder of BuildSync, explains: “It’s almost always the big MEP equipment packages: air handlers, RTUs, chillers, switchgear. One of those packages is a thick stack of cut sheets, drawings, and performance data with hundreds of requirements to check. If the sub leaves out a sound data sheet or submits the wrong voltage, the whole package comes back around. The second review isn’t a quick look either. The engineer has to check the revised sheets and make sure nothing else changed along the way. Firms usually notice too late because most of them don’t track hours by submittal. All the time goes into one big CA bucket, and it only shows up when someone runs the numbers halfway through construction and sees the budget’s already gone.”
The Resubmittal Multiplier: Where Actual Costs Leave the Construction Budget
Construction administration cost overruns often trace back to resubmittals. The fee assumes one review per submittal, and every "revise and resubmit" adds another against the same budget line.
You can run the math with your own numbers: review hours = submittals × average hours per review × review cycles per submittal.
Average review cycles per submittal | Review hours compared with a one-pass budget |
1.0 | 100% (what the fee priced) |
1.3 | 130% |
1.6 | 160% |
2.0 | 200% |
A project that averages 1.6 cycles spends 60% more submittal review hours than the CA budget assumed, before a single unplanned site visit. Resubmittals also cluster early, when long-lead equipment is moving, so actual costs run ahead of plan while the project is young. Corrective action costs least at that stage, yet on many projects nobody tracks review cycles until construction administration cost overruns show up in the budget report.
Slow Reviews Create Cost Escalation Across the Construction Industry
As reviews pile up, response times stretch. In a CSI article on submittal review timeliness, specifier Kevin O'Beirne reports seeing design teams average 28 to 42 or more days to respond to submittals, a pace he warns invites delay claims. The cost of slow and repeat reviews spreads across the project team:
Who absorbs it | What slow or repeat reviews cost them |
Engineering firm | Unbillable CA hours, plus financial exposure and risk management problems if delay claims follow |
General contractor | Rework, resubmittal admin, and schedule pressure on every rejection |
Field crews and the schedule | Crews on the job site waiting on equipment while project timelines slip |
On the contractor side, BuildSync's own survey research puts the average cost of a rejected submittal at $805.
How Do CA Overruns Affect Engineering Firm Profit Margins and Cash Flow?
CA overruns come straight off engineering firm profit margins, because a fixed CA fee turns every extra review cycle into unbillable time. The cost lands late in the project lifecycle, when there's little room left for a fee adjustment.
Thinner Margins Leave Less Room for CA Overruns
The margin cushion is thinner than it was. The Deltek Clarity A&E industry study, in its 47th edition (May 2026), reported operating profit of 16.7% on net revenue, down from a 10-year high of 21.4% in the 2025 edition, with utilization just under 60%.
With margins in that range, a CA phase that runs 30% or 60% over its review budget can wipe out much of the engineering firm project profitability on that job.
The Cash Flow Gap
There's a cash flow effect, too. Under commercial contracts with a fixed CA fee, when costs rise, the design firm absorbs them. Salaries for those extra CA hours go out every week, while the matching fee was billed months earlier or never will be. That gap can strain cash flow just as firms staff up for new projects.
Why CA Is Rarely a Profit Center
The AIA paper shows how rare construction administration profitability is: at a 2014 AIA Convention workshop with more than 50 attendees, only one, a consultant whose entire business is CA, called it a profit center. For the rest, CA was a cost to manage, not a source of profit.
See how BuildSync checks submitted product data against your specs before your engineers open the file. Request a demo.
Reducing Construction Administration Costs: Five Levers for Construction Budget Management
Reducing construction administration costs means controlling two things: how many hours each review takes, and how many reviews each submittal needs. These five levers work on one or both.
1. Price CA by Duration and Expected Review Cycles
AIA recommends estimating the effort construction will require instead of a fixed percentage. Build the CA estimate from the schedule, the expected submittal count, and a review-cycle assumption drawn from historical data on past projects. If your last three hospital jobs averaged 1.5 cycles, price 1.5 cycles.
2. Tighten the Spec Sections That Drive Resubmittals
Vague performance language invites substitutions and partial data. Three changes cut the back-and-forth:
Name acceptable manufacturers where the owner allows it.
State the values you'll check, such as efficiency, refrigerant, coating, and warranty term.
List the required submittal content so partial packages are easy to return.
3. Standardize Review Templates by Equipment Type
An air handler review shouldn't depend on which engineer opens it. A template per equipment type, listing the characteristics to check, cuts review time and keeps quality consistent across project teams, which matters when labor conditions limit how many senior reviewers a firm can staff.
4. Put Review Expectations in the Owner Agreement and Submittal Schedule
Before signing, check what the owner agreement says about repeat reviews and whether excessive resubmittals count as additional services. Then use the schedule of submittals to agree review periods with the contractor. Clear communication upfront prevents disputes when a third resubmittal arrives. Consider spec language that bills substitution reviews at standard rates and limits how many times the team re-inspects the same punchlist item.
5. Automate the Product Data Check That Slows Construction Management
Product data review is the most repetitive part of CA: matching dozens of cut sheet values against a spec section, line by line. Done with traditional methods (a PDF, the spec book, and a highlighter), it's slow and time consuming, and on MEP-heavy jobs it eats a large share of CA hours.
The clerical side adds more: logging, distributing, and chasing submittals takes CA time without needing an engineer's judgment, so it belongs with admin staff or software.
How Automated Product Data Review Supports Construction Project Management
Automated product data review gives the engineer a characteristic-by-characteristic compliance check before manual review starts. BuildSync, an AI-powered submittal review software for engineering firms, breaks each submittal into its individual products, extracts the technical characteristics of each one, and checks every value against the plans and specifications, which are uploaded once per project as shared project information.
Most project management software only tracks where a submittal sits in the workflow, so this content check is work those tools leave to the engineer.
What the Engineer Sees for Each Characteristic
Each characteristic gets a status:
Pass: the submitted value meets the plans and specs.
Fail: it doesn't, with the reason stated.
Unknown: the information is missing from the submittal or ambiguous in the documents, so it needs a human call.

How Engineers Verify the Results
Skepticism about AI checking technical documents is reasonable when an engineer's stamp is on the line. That's why every result links to its source: one click opens the submittal page and spec page side by side, value highlighted, so the engineer verifies the finding instead of hunting for it. If plans and specs contradict each other, BuildSync flags both requirements and notes the more stringent one.

What Stays With the Engineer
The engineer still owns the review and makes the calls on unknowns, substitutions, and design intent. BuildSync reports that teams save 70 to 80% of the time otherwise spent on manual submittal review. On the contractor side, Monteith Construction PM Daniel Recktenwald reported he was able to cut submittal review time by 70% on a hospital renovation.
Catching Problems Before They Reach the Engineer
The same checks also work upstream. If project managers at the general contractor run submittals through BuildSync first, fewer noncompliant packages reach the engineer, which is a direct way to reduce overruns from resubmittals.
Subcontractors use the same checks before packages go to the GC: in the Fountain Electric case study, Shared Services Manager Patrick Bloodsworth reviewed a 500-page lighting submittal in 2 to 3 hours instead of 2 to 3 days.
Drawing revisions are the other common CA time sink. Drawing Change Detection flags which previously reviewed submittals a revision affects, so the team rechecks only those.

As Tom Port, co-founder of BuildSync, explains: “The unknowns are where it gets interesting. On a manual first pass, if a data point isn’t in the package, your eye just skips over it. You’re looking for things that are wrong, so you don’t notice what’s missing. When every characteristic comes back as a pass, a fail, or an unknown, the gaps jump out at you: missing sound data, a seismic certification that was never included, an efficiency rating that isn’t listed. Those are the things that come back to bite you in the field. The fails help too, because you go straight to them instead of hunting. What the output won’t do is make the call. Whether a fail is a dealbreaker or an acceptable deviation, or whether an alternate still meets design intent: that’s engineering judgment, and it stays with the engineer every time.”
Try BuildSync free on your toughest product data submittals and compare the results with your own review. Request a demo to get started.
How Can Firms Track Actual Costs Against the CA Budget on Construction Projects?
Cost tracking against the CA budget takes four numbers, reviewed monthly from the first submittal, and it's the step that turns reducing construction administration costs from a goal into something you can measure. Most firms already have the financial data. The gap is using it as project controls during the job instead of in a post-mortem on completed work.
Metric | What it tells you | Warning sign |
Review cycles per submittal | The first number to move when CA starts to overrun | It climbs above the cycles you priced |
CA hours versus budget, by month | Whether burn matches the submittal workload | Burn stays high after major equipment is approved |
Days in review | Reviewer workload and delay-claim risk | Response times stretch past the agreed review period |
Unknowns resolved by RFI | Where specs left room for interpretation | The same spec sections keep generating RFIs |
Principals and decision makers who track these numbers as work progresses can spot cost variances while the fee still has room. Over time, the same cost data gives the firm a real basis for pricing CA on future work. BuildSync's compliance report adds per-submittal counts of passing, failing, and unknown characteristics, which you can log next to CA hours.
Use the construction submittal review ROI calculator to see what fewer review hours would mean on your next job.
As Tom Port, co-founder of BuildSync, explains: “Hours per submittal. That’s the one. Have your engineers log their time against each submittal for 30 days before and 30 days after, then compare the averages. Count every resubmittal along with the first review, because the repeat cycles are where the margin leaks. Most firms have never measured this, so the first surprise is usually how high the ‘before’ number is. If the ‘after’ number keeps coming down, you’re protecting margin. If it doesn’t, you’ll know fast, and you can have an honest conversation about why.”
Start reducing construction administration costs on your next project. Try BuildSync free on your most complex product data submittals, or request a demo to see how it fits your CA workflow.
Frequently Asked Questions About Construction Administration Costs
Can Engineering Firms Charge for Extra Resubmittal Reviews?
Only when the contract allows it. Check whether the owner agreement treats reviews beyond a set number as additional services, and whether the specifications say who pays for them. Without that language, extra reviews come out of the fixed CA fee.
Does Automated Submittal Review Change the Engineer of Record's Responsibility?
Does BuildSync Review Shop Drawings?
Related reads for you
Discover more articles that align with your interests and keep exploring.